Bannerman Energy Says Bulk Earthworks Contract Around 92% Complete at Namibia Uranium Project

MT Newswires Live
Jun 29

Bannerman Energy (ASX:BMN) said the bulk earthworks contract is advancing in line with schedule, with around 92% completed at its Etango uranium project in Namibia, according to a Monday Australian bourse filing.

The contractor workforce on site now consists of over 560 personnel. The production of heap leach drainage aggregate continues to deliver on-spec material, with around 29% of the total requirement completed.

The civil and mechanical design for the dry plant is around 94% completed.

Its shares rose 2% in recent trading on Monday.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Most Discussed

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10