Bannerman Energy (ASX:BMN) said that the installation of the site water distribution infrastructure was completed at the Etango uranium project in Namibia, according to a Monday Australian bourse filing.
The engineering for the dry processing plant is around 58% complete, per the filing. Meanwhile, detailed engineering on the wet plant is now around 13% complete.
The site access road is around 89% complete, ahead of schedule. A contract for the blasting, crushing, and placement of the drainage layer on the Etango heap leach pads was placed in order to secure costs and supply of the mobile crushing equipment required for the contract.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.