Electric Era just installed six fast EV charging stalls in 54 days from contract to go-live at a Costco in Northport, Florida. That kind of speed is rare in the EV charging world, and it’s thanks to a clever battery-backed system that skips a lot of the usual headaches like grid upgrades and long permitting delays.
Seattle-based Electric Era signed the deal with Costco on April 7, 2025, and had all the drawings and permits in by April 18. Hardware hit the site by mid-May, and by May 30, the site was live with three charger units offering both CCS and NACS plugs. (Electric Era notes that it removed existing EV charging stations, so I wonder whether having existing infrastructure in place sped up the process, even though it needed upgrades.)
The 200 kWh chargers can juice EVs up to 80% in 20 to 60 minutes, and include 24/7 monitoring, automatic fault detection, and over-the-air updates to keep them running smoothly.
Electric Era can move quickly because its patented tech drastically lowers the amount of electricity the site pulls from the grid, making installs easier and reducing grid power consumption by up to 70%. The company also handles everything in-house – from engineering to supply chain to project management – which helped them move from idea to live site in less than two months.
Advertisement - scroll for more contentCEO Quincy Lee says it’s what retailers want: “Our retail customers don’t want their lots torn up for years, they want fast, reliable EV charging systems to help them grow their business and boost their bottom line.” And with grant programs on the line, being able to skip utility upgrades can make a big difference.
But this isn’t just about speed. The North Port Costco installation also includes customer-focused tech like loyalty program integration, point-of-sale connection, and 32-inch screens that retailers can use to run promos and ads. It’s all designed to pull EV drivers into the store and boost sales while they charge.
Electric Era’s chargers are no slouch on performance either. The company says its systems have a 98.5% uptime per port and more than 90% session reliability, with a 96% positive rating on PlugShare. That’s enough to qualify them for Tesla’s Third Party Charging program.
And behind all this is a “skunk works” team of former SpaceX engineers in Seattle, using a “first principles engineering process” to rethink and evaluate every step of the system, from system engineering and project management to parts procurement and system assembly.
As more EV drivers hit the road, stores want charging stations that not only work but also bring in high-value customers.
Read more: With a $30M raise, SparkCharge takes EV fleet charging off-grid
If you’re considering going solar, it’s always a good idea to get quotes from a few installers. To make sure you find a trusted, reliable solar installer near you that offers competitive pricing, check out EnergySage, a free service that makes it easy for you to go solar. It has hundreds of pre-vetted solar installers competing for your business, ensuring you get high-quality solutions and save 20-30% compared to going it alone. Plus, it’s free to use, and you won’t get sales calls until you select an installer and share your phone number with them.
Your personalized solar quotes are easy to compare online and you’ll get access to unbiased Energy Advisors to help you every step of the way. Get started here.
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.